Chemical Recovery Boiler – Rebuild & Capacity Upgrade

Capacity increased by 60% for Satia Industries Ltd

Chemical Recovery Boiler – Rebuild & Capacity Upgrade

Mill Site Location: Satia Industries Ltd, Muktsar, Punjab

Reotech has upgraded Chemical Recovery Boiler (RB#2) for highest capacity of 63% from 400 to 650 tds/d with supply planned and completed in very short time frame of four and a half months, which is first of its kind in the nation.

• Pressure parts rebuild
• New Furnace Floor
• Upgraded multilevel air system
• Upgraded black liquor system
• Modified new superheaters
• Modified new Economiser

The result of this recovery boiler rebuild are

• High increase in Capacity
• Higher runability
• Improved Environmental performance